| July 27 | Draft concept plans revealed publicly and feedback sought |
| August 18 | Feedback on draft concept plans due in by 5pm |
| Mid September | Next set of plans publicised and further discussion sought |
| Late September | Any further feedback due |
| Early October | Resource consent application lodged |
| March/April | If required, resource consent application hearing |
| Early 2008 | If consent is granted, demolition of the old No. 1 - 3 Stands could begin |
| Mid 2008 | Construction of new East Stand could begin |
| Early 2010 | New East Stand completed in time for the Super 14 |